Station 7 Gets A New Look

Inside this issue:

District Updates

1

Flood Control Plan

2

Events

3

Want to Contribute? 4

Contact Us

4

Special points of interest:

Sneak Peak of Station 7 (Site walk)- Yesterday the construction committee had a walkthrough of Station 7 with JE Dunn and Martinez Architects reviewing apparatus bays, the locations of all the speakers, televisions, communication outlets and panels, cameras, keypads, telephones, etc. The walk through was to confirm the overall layout and to make any design or engineering changes. The two-story fire station is still on schedule and we will continue to keep everyone posted on it. With the skin ongoing but coming to an end this month and main power preparation underway, this facility will soon be ready for permanent power and overhead inspection.